Western Australia, 17 November 2026: Delta Lithium (ASX: DLI) has released its Mt Ida scoping study. The plan covers an 11-year operation in the Eastern Goldfields. One site would deliver three products: spodumene, lepidolite and tantalum concentrates.
The project is wholly owned by Delta. It sits 100km northwest of Menzies. Kalgoorlie is roughly 220km away by road. The company says Mt Ida is fully permitted for open pit and underground mining. Updates are still needed for the processing plant and tailings facility.
Mt Ida Lithium Project Study Delivers Headline Numbers
So what did the study find? It points to a production target of approximately 8.5Mt at an average grade of 1.09% Li2O. That runs across 11 years. Post-tax NPV is A$748M at an 8% discount rate. IRR is 33%, and payback takes 4.3 years. Free cash flow totals A$1,415M. Pre-production capital is A$483M, including A$64M of contingency.
Now for the fine print. The study is accurate to +/- 40%. It cannot support Ore Reserves. About 73% of the production target is Measured and Indicated. The remaining 27% is Inferred. Those firmer categories make up 83% of the first five years. That window also covers the payback period.

Location of Delta’s lithium projects in Western Australia, as shown in the company’s study. [Delta Lithium]
How the Mt Ida Lithium Project Would Operate
Mining would begin with open pits at Sister Sam and Timoni. Underground work follows, using long-hole open stoping with paste backfill. Sister Sam supplies roughly 75% of the production target. Sparrow would be reached through a boxcut. A 1Mtpa whole ore flotation plant would process everything on site.
Concentrates would head to Geraldton Port by road train. The route is about 950km one way. Power would come from a build-own-operate diesel station. Delta also sees possible synergies with Ballard Mining (ASX: BM1). Ballard holds the gold rights under an existing Mineral Rights Agreement. More detail sits in Delta’s ASX announcement.
Three Products Behind Delta Lithium Production Plans
Delta Lithium production would centre on three concentrates. Here is what the study expects each year:
- Spodumene concentrate (SC5.5%): about 65kt per annum.
- Lepidolite concentrate (LC3.0% Li2O, 1.8% Rb2O): about 110kt per annum.
- Tantalum concentrate (Ta2O5 5%): about 1.7kt per annum.
- Recoveries: lithium 73%, tantalum 55% and rubidium approximately 60%.
Why Rubidium Matters to the Mt Ida Lithium Project
Rubidium is the quiet star of this study. Here is why it deserves attention:
- Resource scale: Delta says Mt Ida hosts one of the largest, highest-grade rubidium oxide resources published worldwide.
- Critical status: Most Western governments classify rubidium as a critical mineral.
- Market price: Shanghai Metals Market quoted rubidium carbonate at US$1,278/kg on 24 September 2026.
- Cautious credit: The study applies only US$671 per tonne of lepidolite concentrate. That is under 5% payability.
- Contained metal: The lepidolite concentrate holds 19kt of Rb2O.
Costs, Funding and Timing Delta Lithium Must Navigate
Turning a study into a mine takes money and patience. These are the markers to watch:
- Operating costs: Mining is A$116/t mined. Processing and tailings are A$41/t processed. Site administration is A$22/t processed. Transport is A$227/t of concentrate.
- Funding need: Pre-production funding of approximately A$500M may be required. Peak negative cash flow is approximately A$498M in Month 15.
- Balance sheet: Delta held A$48.8M in cash at 30 September 2026. It also holds about A$100M in ASX-listed equities.
- Timeline: Drilling and studies to a final investment decision are assumed to take 2-3 years. Plant construction then takes about 15 months.
- Price exposure: Benchmark Minerals forecasts SC6 at US$2,580 per tonne from 2037. Economics are more sensitive to commodity prices and exchange rates than to costs.
There are no sales agreements in place yet. Funding is not guaranteed either.
For investors, the Mt Ida Lithium Project is still a study-stage story. Delta Lithium ASX watchers should track infill drilling, rubidium marketing and funding news. Those steps will decide whether this 11-year plan becomes a real operation.
Also Read: Gorilla Gold Expands Its Western Australian Gold Portfolio With Strategic Cosmos Acquisition
Mt Ida Lithium Project FAQs
Q1: What is the Mt Ida Lithium Project?
A1: It is a 100%-owned Delta project 100km northwest of Menzies. The area covers 364 km2 and includes Sister Sam, Timoni and Sparrow.
Q2: How much could it produce?
A2: The plan targets 8.5Mt at 1.09% Li2O over 11 years at 1Mtpa. Annual output is about 65kt of SC5.5, 110kt of LC3.0 and 1.7kt of tantalum concentrate.
Q3: When could production begin?
A3: Delta assumes 2-3 years to reach a final investment decision. Plant construction then takes about 15 months, and the first pit delivers tonnes within 1 month of mining.
Q4: How much funding is needed?
A4: Pre-production funding of approximately A$500M may be required. Capital is estimated at A$483M, against cash of A$48.8M at 30 September 2026.
Disclaimer:
This article summarises a preliminary scoping study released by Delta Lithium. Twenty-seven per cent of the production target relies on Inferred resources. Funding is not secured, and no sales agreements are in place. Figures are forward-looking. Please always consult a licensed adviser before investing.
Luke Carlino is a seasoned Copywriter, Content Strategist, and Social Media Manager specialising in Mining, Finance, and Business journalism. With more than a decade of industry experience, he brings rigorous editorial standards and commercial acuity to every project.